Oceania Dairy’s staff have moved into the office building at the company’s new Glenavy processing plant.
A total of 63 staff are now located on site in advance of completion of the new factory.
“Our…
The deconstruction of the Favco tower crane from the dryer at the new Oceania Dairy Glenavy processing plant is a strong indication that the factory build is nearing completion.
The crane has been on…
The commissioning programme for Oceania Dairy’s new $214 million Glenavy milk processing plant is scheduled to commence in July.
The commissioning programme will mark the final stage of the 14 month…
Oceania Dairy has exceeded its supply target of 130 million litres for the first season of operation of its new Glenavy factory.A total of 46 suppliers have signed contracts with Oceania for the supp…
Overview of Project Progress
Construction of the Glenavy milk factory has stepped up another gear, with the installation of the dryer and the calandrias in the 47 metre dryer tower. The generating ba…
Overview of Project Progress
The overall project is on target for completion in time to take milk in August 2014.
Work on the underground services on site is now complete and roading preparation work…
Oceania Dairy Limited has signed its first milk supply agreement for its new $214 million Glenavy dairy factory. Oceania Dairy Limited is a wholly owned subsidiary of Inner Mongolia Yili Industrial G…
Overview of Project Progress
The overall project is on target for completion in time to take milk in August 2014.
The dryer tower has reached 21 metres, just under halfway to its final height of 47 m…
A significant road-works project on State Highway 1 at Glenavy will commence in early October to prepare for the opening of the $214 million Oceania Dairy processing plant.
A slip lane, turning lane…